Do lien waivers have to be notarized?
2026-09-04 · 5 min read

The answer is jurisdictional. A minority of states publish a waiver form and say how it is executed; everywhere else the subcontract decides. Here is how to work out which case you are in.
The short answer
Usually no, sometimes yes, and the answer is set by the state where the property sits — not by the state you are incorporated in and not by the general's policy. A minority of states publish a statutory waiver form and prescribe how it must be executed; the rest leave execution to the contract.
Because the rule is jurisdictional, the practical question on any given job is narrower: does this state prescribe a form, and does this subcontract require notarisation on top? Both can be true, and the contract can demand more than the statute does.

Statutory forms change the calculation
Where a state publishes the form, deviation is risky. Florida sets out the waiver language in its lien statute — including the sentence that a progress waiver does not cover retention or work after the stated date. Using a general's in-house form in a state like that invites an argument about whether the document did what the statute says a waiver does.
Where no statutory form exists, the waiver is a contract document and the ordinary rules apply: it means what it says, and ambiguity is construed against the drafter — which is usually not you.
| Question | Where the answer lives | If unclear |
|---|---|---|
| Is there a statutory form? | The state lien statute | Use the statutory language verbatim |
| Notarisation required? | Statute, then the subcontract | Notarise; it costs little |
| Witness required? | Statute | Add one; it is never harmful |
| Recording required? | Only for lien releases | Waivers are not recorded |
What to do in practice
- Look up the state where the property sits, not where you are based.
- If a statutory form exists, use its words. Do not paraphrase.
- If the subcontract requires notarisation, notarise even where the statute does not.
- Notarise anything you sign unconditionally — the cost is trivial next to the release.
- Keep the notarised original; send a scan.
Notarisation proves who signed, not that the signer had authority. If a project manager signs a final waiver they were not authorised to sign, the notary block does not fix that — and the general will still rely on it.
Lien releases are different
A release of a recorded lien is a recorded instrument, and recorded instruments almost always require acknowledgement before a notary. That is a separate question from waivers, and the answer there is much closer to a flat yes.
Draft the release with the lien release generator, then take it to a notary and record it with the same county that holds the original claim.

Sources
- Fla. Stat. § 713.20(4)
Florida publishes a statutory waiver form. The progress-payment version states that it does not cover retention, or labor, services or materials furnished after the date written on it.
Read 2026-09-04
- Cal. Civ. Code § 8200
Before recording a lien, giving a stop payment notice or claiming against a payment bond, a California claimant must give preliminary notice to the owner, the direct contractor and the construction lender. A laborer is exempt.
Read 2026-09-04