Lien waiver requirements by state
2026-09-04 · 7 min read

Waiver rules are set by the state where the property sits. A minority publish the form itself; the rest leave it to the subcontract. Here is what three of the biggest construction states actually say.
Two camps, and which one you are in
States fall into two groups. In the first, the lien statute sets out waiver language and the form is effectively mandatory — Florida is the clearest example we read directly, publishing the waiver-on-progress-payment text in its lien chapter. In the second and much larger group, no statutory form exists and the waiver is whatever the subcontract says it is.
You need to know which camp the property's state is in before you sign anything. A national general operating in twelve states will hand you one in-house form for all twelve, and in the statutory-form states that form may not do what a statutory waiver does.

Florida, read directly
Florida's statute prints the waiver form. The progress-payment version recites the consideration, names the customer, the owner and the property, and then says the release “does not cover any retention or labor, services, or materials furnished after the date specified”. Two protections in one sentence, granted by statute rather than by negotiation.
Florida also sets the notice clocks that surround the waiver: a lienor not in privity with the owner serves the Notice to Owner before starting or within 45 days of starting, and the claim of lien is recorded no later than 90 days after final furnishing.
| Item | Rule | Cite |
|---|---|---|
| Notice to Owner | Before start, or within 45 days | § 713.06(2)(a) |
| Claim of lien | Within 90 days of final furnishing | § 713.08(5) |
| Progress waiver form | Published in the statute | § 713.20(4) |
Texas and California
Texas does not publish the same style of waiver text in the sections we read, but it does something unusual with money: the owner must reserve 10 percent of the contract price during the work and for 30 days after completion, and a claimant reaches those reserved funds by sending the required notices and filing an affidavit no later than the 30th day after completion.
California's architecture is notice-first. Before recording a lien, giving a stop payment notice or claiming against a payment bond, a claimant must give preliminary notice to the owner, the direct contractor and the construction lender — and that notice is due within 20 days of first furnishing work. A waiver signed by a claimant that never served the notice may be releasing a right that was never preserved.
Lien deadline
In California the claim of lien is due before the earlier of 90 days after completion or 60 days after a recorded notice of completion for a direct contractor — 30 days for everyone else. Track your own dates on the deadline calculator.
A four-line checklist for any state
- Where is the property? That state's law governs.
- Does that state publish a waiver form? If yes, use its words.
- What notice was required before the waiver, and did you serve it?
- Does the subcontract add notarisation, witnesses or a specific form?
Where you cannot answer line two from the statute itself, treat the general's form as a contract document and read it as one. The pages on this site cite the statute text for every state figure they state, with the date it was read.

Sources
- Fla. Stat. § 713.06(2)(a)
A Florida lienor not in privity with the owner must serve the Notice to Owner before commencing, or not later than 45 days after commencing, to furnish labor, services or materials.
Read 2026-09-04
- Fla. Stat. § 713.08(5)
A Florida claim of lien may be recorded at any time during the work but not later than 90 days after the final furnishing of labor, services or materials by the lienor.
Read 2026-09-04
- Fla. Stat. § 713.20(4)
Florida publishes a statutory waiver form. The progress-payment version states that it does not cover retention, or labor, services or materials furnished after the date written on it.
Read 2026-09-04
- Tex. Prop. Code § 53.101
Texas requires the owner to reserve 10 percent of the contract price (or 10 percent of the value of the work) during the job and for 30 days after completion — statutory retainage.
Read 2026-09-04
- Tex. Prop. Code § 53.103
A Texas claimant reaches the reserved funds by sending the required notices and filing a lien affidavit no later than the 30th day after the work is completed, the contract terminated, or performance abandoned.
Read 2026-09-04
- Cal. Civ. Code § 8200
Before recording a lien, giving a stop payment notice or claiming against a payment bond, a California claimant must give preliminary notice to the owner, the direct contractor and the construction lender. A laborer is exempt.
Read 2026-09-04
- Cal. Civ. Code § 8204
The California preliminary notice is due no later than 20 days after the claimant first furnishes work. A late notice still works, but it reaches back only 20 days before service.
Read 2026-09-04
- Cal. Civ. Code § 8412
A California direct contractor must record its claim of lien before the earlier of 90 days after completion of the work of improvement, or 60 days after the owner records a notice of completion or cessation.
Read 2026-09-04
- Cal. Civ. Code § 8414
A California claimant who is NOT the direct contractor must record before the earlier of 90 days after completion, or 30 days after the owner records a notice of completion or cessation.
Read 2026-09-04