Florida's construction lien law is Part I of chapter 713 of the Florida Statutes, and it is stricter on paper than most. The notices have their own forms, the waivers have their own forms, and a single late notice ends the lien. This guide walks a Florida job from the notice of commencement to the lawsuit, with every number read from the 2026 statutes on 2026-10-18. For the same dates in California, Texas and on federal jobs, see mechanics lien deadlines by state.

The notice of commencement is your address book

Before work starts, the owner records a notice of commencement with the clerk and posts a certified copy (or a notarized statement that it was filed, with a copy) on the job. It lists the legal description, the owner, the contractor, the surety and bond amount if there is a payment bond, the construction lender, and anyone the owner designates to receive notices. Only the owner may sign it.

For a subcontractor or supplier, this document is the most useful page in the job file. Notices sent to the last address shown in it count as served on the mailing date even if they come back refused or unclaimed, and if the address is incomplete you may fix it from the property appraiser's records. With no notice of commencement on record, you can rely on the building permit application instead.

  • Work not started within 90 days of recording: the notice is void. § 713.13(2)
  • It expires 1 year after recording unless it states a later date; owner payments after expiry are improper payments. § 713.13(1)(c), (6)
  • Changing contractors takes a new notice of commencement, not an amendment. § 713.13(5)(a)

Pull a copy from the county clerk the week you get the purchase order. If the owner named a designee or a lender to receive notices, they get your Notice to Owner too.

Notice to Owner: 45 days, and no grace

Every lienor not in privity with the owner, except laborers, must serve a Notice to Owner before it can perfect a lien. It goes out before you start, or not later than 45 days after you first furnish labor, services or materials. It also has to land before the owner disburses final payment after the contractor has given its final payment affidavit, so on a short job the practical deadline can come sooner than day 45.

Who serves the Florida Notice to Owner
Your tierServe onCite
Contractor (contract with the owner)No NTO. It is in privity with the owner.§ 713.05
Subcontractor (contract with the contractor)Owner§ 713.06(2)(a)
Sub-subcontractor, or supplier to a subOwner, plus a copy to the contractor§ 713.06(2)(a)
Supplier to a sub-subcontractorOwner and contractor, plus the sub if its name and address are known§ 713.06(2)(a)
LaborerExempt from the notice§ 713.06(2)(a)

The statute is blunt about timing. Errors in the content of the notice can be forgiven where nobody was hurt by them, but the lienor “must strictly comply with the time requirements,” and failing to serve, or serving late, is a complete defense to the lien. The notice must carry the statutory warning in capitals that tells the owner it may pay twice unless it collects a written release every time it pays the contractor.

The safest service route is certified, registered or Global Express Guaranteed mail sent within 40 days of first furnishing, with a mail log showing the USPS number and date stamp, or USPS tracking records. Do that and service is effective on the date of mailing, which takes the post office out of your deadline. Our Florida Notice to Owner generator drafts the notice with the statutory warning, and the preliminary notice guide compares it with the California and Texas versions.

Lien deadline

Count day 45 from your first delivery or first day on site, not from the date of the subcontract. If day 45 is a weekend or court holiday it rolls to the next business day, but plan on the day-40 mailing date and never test the roll-forward.

Claim of lien: 90 days from final furnishing

Every lienor, contractors and laborers included, perfects its lien by recording a claim of lien in the clerk's office of the county where the property sits, and in each county if it straddles a line. You can record at any time during the work, but not later than 90 days after your final furnishing of labor, services or materials. The claim is signed and sworn to, or affirmed, by you or an agent who knows the facts, and it carries the statute's warning that the lien may stay valid for one year from recording.

  1. 01Your name, and the address where notices and process can be served on you
  2. 02Who you contracted with or were employed by
  3. 03The labor, services or materials and their contract price or value (specially fabricated, uninstalled materials listed separately)
  4. 04A legal description of the property good enough to identify it, and the owner's name
  5. 05The dates of your first and last furnishing
  6. 06The amount unpaid, including unpaid finance charges due under your contract
  7. 07If you are not in privity with the owner: the date and method of serving your Notice to Owner (and the copies on the contractor or sub, where required)

Final furnishing has a statutory meaning and it is narrower than most people assume. It is the last date you furnished labor, services or materials. A certificate of occupancy or certificate of final completion does not set it, and coming back to correct deficiencies in your own work does not extend it. For rental equipment it is the last day the equipment was on site and available for use. If the owner terminates the prime contract, the window becomes the earlier of 90 days after termination or 90 days after your final furnishing.

Then serve the recorded claim on the owner, before recording or within 15 days after. Late or missing service makes the claim voidable to the extent it prejudiced someone entitled to rely on it, which is a fight you do not need. The mechanics lien form builder lays out the fields in this order, and the mechanics lien deadline calculator gives you the day-45 and day-90 dates for a Florida job from the two dates you enter.

You can amend a recorded claim at any time inside the recording window. An amended claim that shows a later final furnishing date also restarts the 1-year enforcement clock from the amendment's recording.

A worked timeline, first board to lawsuit

A drywall subcontractor signs with the general contractor on a retail build-out. It has no contract with the owner, so it is a lienor not in privity and needs a Notice to Owner. The job closes out with $7,400.00 of retainage still unpaid. Here is every date that matters, worked from the statute.

Worked Florida lien timeline, one subcontractor
DateEventRuleCite
2026-03-05Crew starts hanging board (first furnishing)Day 0 for the Notice to Owner§ 713.06(2)(a)
2026-04-14Mail the NTO by certified mail, keep the mail logService effective on mailing if mailed within 40 days§ 713.18(2)
2026-04-19Day 45 falls on a SundayRolls to the next business day§ 713.011(1)
2026-04-20Last day to serve the NTOStrict: late service is a complete defense§ 713.06(2)(a), (f)
2026-08-14Last board hung and finished (final furnishing)Punch-list fixes later do not move this date§ 713.01(12)
2026-10-20Claim of lien recorded with the clerkAny time up to 90 days after final furnishing§ 713.08(5)
2026-11-04Last day to serve the recorded claim on the ownerWithin 15 days after recording§ 713.08(4)(c)
2026-11-12Outside edge for recording, had it waited90 days after final furnishing§ 713.08(5)
2027-10-20Suit to enforce must be on file1 year after recording§ 713.22(1)

Two things in that table catch people. Waiting on retainage does not move final furnishing: the clock started on August 14 when the last board went up, not when the general said the retention would be released. And if the owner records a notice of contest and the clerk serves it on, say, January 8, 2027, the 1-year suit window collapses to 60 days from that service, which puts the deadline at March 9, 2027.

One year to sue, or 60 days after a contest

A Florida lien lasts no longer than 1 year after the claim is recorded unless an action to enforce it is filed in that time. Once suit is filed, record a notice of lis pendens as well; without one the lien is not enforceable against creditors or later buyers who paid value without notice.

The owner can shorten that year. By recording a notice of contest of lien, the owner or its attorney cuts your time to sue to 60 days from service of the notice. The clerk serves it on you at the address in your claim of lien, which is why that address has to be one somebody actually opens. Miss the 60 days and the lien is extinguished automatically, with no hearing.

Florida enforcement windows
TriggerDeadline to sueCite
Claim of lien recorded1 year§ 713.22(1)
Amended claim with a later final furnishing1 year from the amendment§ 713.22(1)
Notice of contest served on you60 days§ 713.22(2)
Contractor's final payment affidavit5+ days before suit§ 713.06(3)(d)1.

The last row is for contractors only, the party with the contract with the owner. Before filing to enforce its lien, the contractor must deliver a sworn final payment affidavit to the owner at least 5 days ahead, listing every lienor who served a timely Notice to Owner and is still unpaid, with the amount. The duty applies even if the contract was terminated before completion, and even if the contractor had no subs or suppliers at all. A contractor in default on the affidavit has no lien or right of action against the owner for the work under that contract until it cures.

Florida waivers: the statute writes the form

Section 713.20 prints two waivers, one for a progress payment and one for final payment. The progress form says it does not cover retention or anything furnished after the date written on it. Four other rules in the same section shape what you sign at the pay-app table.

  • No advance waivers. A lien right can be waived only for work already furnished; a waiver given in advance is unenforceable. § 713.20(2)
  • Nobody may require you to sign a waiver that differs from the statutory forms. § 713.20(6)
  • A waiver given for a check can be conditioned on the check clearing. § 713.20(7)
  • But a non-statutory waiver you do sign is enforced on its own terms, so read the general's form before you sign it. § 713.20(8)

In the worked example, every progress waiver the drywall sub signed left its retainage outside the release, which is exactly why it still had something to lien. The final waiver is the one that gives that up, so it goes out only against cleared funds. The lien waiver state requirements guide sets Florida beside the states with no statutory form, and the final lien waiver generator drafts the closing release once the money is in.

Lien the real number, or lose the lien

Florida punishes padding. A lien is fraudulent if the lienor willfully exaggerated the amount, willfully included work not performed or materials not furnished to that property, or compiled the claim with such willful and gross negligence that it amounts to the same thing. A fraudulent lien is a complete defense to enforcement: the court declares it unenforceable and you forfeit the lien.

It gets worse from there. The owner, or a contractor or sub damaged by the filing, can sue you for damages, including attorney's fees, the premium on a bond posted to discharge the lien, and punitive damages up to the difference between what you claimed and what was actually due. Willfully filing a fraudulent lien is a third-degree felony.

The statute protects honest disagreement: a minor mistake, or a good-faith dispute over the amount due, is not willful exaggeration. Lien the unpaid contract balance plus any finance charges your contract actually provides for, back it with the pay apps and change orders, and leave out the claims you could not prove.

Sources

  • Fla. Stat. § 713.06(2)(a)

    A Florida lienor not in privity with the owner must serve the Notice to Owner before commencing, or not later than 45 days after commencing, to furnish labor, services or materials.

    Read 2026-10-18

  • Fla. Stat. § 713.08(5)

    A Florida claim of lien may be recorded at any time during the work but not later than 90 days after the final furnishing of labor, services or materials by the lienor.

    Read 2026-10-18

  • Fla. Stat. § 713.20(4)

    Florida publishes a statutory waiver form. The progress-payment version states that it does not cover retention, or labor, services or materials furnished after the date written on it.

    Read 2026-10-18

  • Fla. Stat. § 713.06(2)(a), (c), (f)

    Laborers are exempt from the Notice to Owner. A sub-subcontractor or supplier to a subcontractor also serves a copy on the contractor; a supplier to a sub-subcontractor serves the contractor and, if known, the subcontractor. The notice must also precede the owner's final payment after the contractor's affidavit, carry the statutory warning, and meet the time limits strictly; late service is a complete defense.

    Read 2026-10-18

  • Fla. Stat. § 713.05

    A contractor, or a materialman or laborer in privity with the owner, acquires its lien by recording a claim of lien and is not required to serve a Notice to Owner.

    Read 2026-10-18

  • Fla. Stat. § 713.08(1)-(3), (5)

    The claim of lien states the lienor, its customer, the work and its value, the property, the owner, the first and last furnishing dates, the unpaid amount and (for a non-privity lienor) how the Notice to Owner was served. It is sworn, recorded in each county where the property lies, and after a termination under s. 713.07(4) is due by the earlier of 90 days after termination or after final furnishing.

    Read 2026-10-18

  • Fla. Stat. § 713.13(1), (2), (6)

    Before work starts the owner records a notice of commencement and posts it on the job. It is void if the improvement is not commenced within 90 days of recording, and it expires 1 year after recording unless it states a later date.

    Read 2026-10-18

  • Fla. Stat. § 713.18(2), (3)

    A Notice to Owner mailed by registered, Global Express Guaranteed or certified mail within 40 days after first furnishing, with a USPS mail log or tracking record, is served as of the date of mailing. Mail to the last address in the notice of commencement is served even if returned refused or unclaimed.

    Read 2026-10-18

  • Fla. Stat. § 713.011(1)

    A time period under Part I that ends on a Saturday, Sunday or holiday is extended to the end of the next business day.

    Read 2026-10-18

  • Fla. Stat. § 713.01(12)

    Final furnishing is the last date the lienor furnishes labor, services or materials. It is not set by a certificate of occupancy or final completion and does not include correcting deficiencies in the lienor's own work.

    Read 2026-10-18

  • Fla. Stat. § 713.08(4)(c)

    The claim of lien must be served on the owner before recording or within 15 days after recording; failure makes it voidable to the extent the failure prejudiced someone entitled to rely on service.

    Read 2026-10-18

  • Fla. Stat. § 713.06(3)(d)1.

    A contractor must deliver its sworn final payment affidavit to the owner at least 5 days before suing to enforce its lien, even if the contract was terminated and whether or not it had lienors under it.

    Read 2026-10-18

  • Fla. Stat. § 713.22(1), (2)

    A lien lasts no longer than 1 year after the claim (or an amended claim showing a later final furnishing) is recorded unless suit is filed. An owner's recorded notice of contest cuts the time to sue to 60 days from service; the lien is then extinguished automatically if no suit is filed.

    Read 2026-10-18

  • Fla. Stat. § 713.20(2), (6)-(8)

    A lien right may not be waived in advance; nobody may require a waiver different from the statutory forms; a waiver given for a check may be conditioned on payment; a non-conforming waiver is enforceable on its terms.

    Read 2026-10-18

  • Fla. Stat. § 713.31(2), (3)

    A willfully exaggerated lien, or one including work not performed, is fraudulent: the lien is forfeited, the lienor is liable for damages including punitive damages, and willful filing is a third-degree felony. A minor mistake or good-faith dispute is not fraud.

    Read 2026-10-18