Skip to content

Mechanics lien in Texas: notices and deadlines

2026-10-1810 min read

Texas does not run its lien clocks in days. It runs them in months, and every unpaid month of work gets its own notice deadline. That is why a Texas claim fails more often on a missed notice than on a missed filing. This guide walks through chapter 53 of the Property Code as it reads today, after the 2022 rewrite, with one job worked from the first unpaid invoice to the suit date. If the idea of a lien is new to you, start with what a mechanics lien is.

Who can claim a Texas lien

Texas splits every claimant into two kinds. An original contractor is anyone who contracts with the owner, directly or through the owner's agent. Everyone below it is a derivative claimant: the subcontractor of any tier, and the supplier who sells to the original contractor or to a sub. Labor, material, specially fabricated material that was never delivered, design work by a licensed architect, engineer or surveyor, landscaping and demolition all carry lien rights (§ 53.021).

The split decides everything that follows. The original contractor owes no monthly notice and files on its own completion date. A derivative claimant owes the owner a notice for every unpaid month, and its lien is capped at the earned share of its subcontract minus what it has already been paid (§ 53.024). One escape hatch: if the “general” you signed with is controlled by the owner and was put there to dodge the notice rules, you are treated as an original contractor (§ 53.026).

Texas lien claimants by tier: notice owed and affidavit deadline
ClaimantWho it isNotice before filingAffidavit due (non-residential)
Original contractorContracts with the owner, directly or through the owner's agentNo notice of claim under § 53.05615th day of the 4th month after the month its work was completed, terminated or abandoned (3rd month residential)
Subcontractor, any tierWorks under the original contractor or under another subNotice of claim to the owner and the original contractor for each unpaid month15th day of the 4th month after the month it last provided labor or materials (3rd month residential)
SupplierFurnishes material to the original contractor or a subcontractorSame monthly notice of claimSame as a subcontractor
Retainage claimantAny derivative claimant owed retainage under its contractNotice of claim for unpaid retainage (§ 53.057), unless the monthly notices already covered it15th day of the 3rd month after the month the original contract was completed, terminated or abandoned

The monthly notice of claim

Texas has no start-of-job preliminary notice. Its clock starts when a month goes unpaid. For every month of labor or material you have not been paid for, send a notice of claim to the owner (or reputed owner) and the original contractor by the 15th day of the third month after the month you did the work. On a residential project it is the 15th day of the second month. Miss it and the lien for that month is gone, even if later months are still alive.

Monthly notice deadlines by month worked
Month workedCommercial notice byResidential notice by
JanuaryApril 15March 15
MayAugust 15July 15
JuneSeptember 15August 15
OctoberJanuary 15December 15

The notice has a statutory form, and the safest notice is the form itself with the blanks filled in. You may attach the invoice or billing statement. Send it in person, by certified mail, or by a traceable private carrier that confirms receipt; certified mail counts as given the day you deposit it (§ 53.003). If the 15th lands on a Saturday, Sunday or legal holiday, the deadline moves to the next business day (§ 53.003(e)) — but mail it a week early and you never need that rule.

Read the statutory notice text (§ 53.056(a-2))

NOTICE OF CLAIM FOR UNPAID LABOR OR MATERIALS

WARNING: This notice is provided to preserve lien rights.

Owner's property may be subject to a lien if sufficient funds are not withheld from future payments to the original contractor to cover this debt.

Date: ______________

Project description and/or address: ______________

Claimant's name: ______________

Type of labor or materials provided: ______________

Original contractor's name: ______________

Party with whom claimant contracted if different from original contractor: ______________

Claim amount: ______________

______________ (Claimant's contact person)

______________ (Claimant's address)

Why the owner cares: once it receives your notice it may hold back enough from the original contractor to cover your claim (§ 53.081), and money it keeps paying out after that can come back on its property if your lien is perfected and reduced to judgment (§ 53.084). That is the pressure the notice buys. A separate past-due notice to the original contractor alone is allowed but optional (§ 53.056(a-4)).

A worked timeline

An HVAC subcontractor signs with the general contractor on an office build-out in Austin: a $148,000.00 subcontract with 5 percent retainage. It works March through June 2026 and finishes its last ductwork on Friday, June 26, which completes its subcontract. March and April are paid. The May pay application ($26,600.00 net) and the June one ($19,000.00) never are, and $7,400.00 of retainage is still held. The general finishes its own contract on Friday, September 18. Every date below is counted from the statute.

Month ledger of the worked example, May to December 2026
ClaimMayJunJulAugSepOctNovDec
May workworkednotice 17th
June workworked, off site 26thnotice 15th
Retainagenotice 27thaffidavit 15th
Lien affidavitfile by 15th
10% reserveGC done 18thaffidavit 19th

Red marks a deadline. Each unpaid month runs its own clock.

Worked Texas lien deadlines with citations
DeadlineWhat is dueHow it is countedCite
2026-07-27Retainage notice to owner and GC30th day after the subcontract was completed (Jun 26) is Sunday Jul 26; rolls to Monday§ 53.057(a-1)
2026-08-17Notice of claim for May work15th day of the 3rd month after May is Saturday Aug 15; rolls to Monday§ 53.056(a-1)(1)
2026-09-15Notice of claim for June work15th day of the 3rd month after June§ 53.056(a-1)(1)
2026-10-15Lien affidavit filed with the county clerk15th day of the 4th month after June, the last month worked§ 53.052(b)
+5 daysCopy of the filed affidavit to owner and GCNo later than the 5th day after the filing date§ 53.055
2026-10-19Affidavit on file to reach the owner's reserve30th day after the GC finished (Sep 18) is Sunday Oct 18; rolls to Monday§ 53.103
2026-12-15Outside edge for a retainage-only affidavit15th day of the 3rd month after September, the month the original contract was completed§ 53.052(d)
2027-10-15Suit to foreclose on fileFirst anniversary of the last day to file the affidavit§ 53.158(a)

How we would run it: mail each notice the week a pay application goes 30 days unpaid, not in the week it is due. Then file one affidavit covering May, June and the retainage on Friday, October 9, which beats both the October 15 affidavit date and the October 19 reserve date, and get the copies out by Wednesday, October 14. That puts the whole $53,000.00 on the record with room to spare, and the one date left to diarise is October 15, 2027.

Same sub, same months, on a house. The May notice is due July 15, the June notice August 15 (a Saturday, so Monday August 17), and the affidavit September 15, the 15th day of the third month after June. A residential job takes a month off every clock.

Filing the lien affidavit

A Texas lien is perfected by filing a sworn affidavit with the county clerk in the county where the improvements are located (§ 53.052(e)). The deadline is the 15th day of a later month, counted from a month, not from a day, so work finished on the 1st and on the 30th of the same month gets the same date.

Texas lien affidavit deadlines under section 53.052
ClaimantCounted fromCommercialResidential
Original contractorMonth its work was completed, terminated or abandoned15th of month 415th of month 3
Sub or supplierMonth it last provided labor or materials15th of month 415th of month 3
Retainage claim (derivative)Month the original contract was completed, terminated or abandoned15th of month 315th of month 3

The affidavit is signed by you or someone on your behalf and must contain, substantially, the eight items below (§ 53.054). It does not need line items; trade abbreviations are fine. You may attach the contract and copies of each notice you sent, and on a disputed claim you should.

  1. 01A sworn statement of the amount of the claim
  2. 02The name and last known address of the owner or reputed owner
  3. 03A general statement of the work done and materials furnished, and for a derivative claimant each month the work was done
  4. 04The name and last known address of whoever hired you or bought your materials
  5. 05The name and last known address of the original contractor
  6. 06A legal description of the property, good enough to identify it
  7. 07Your name, mailing address and, if different, physical address
  8. 08For a derivative claimant, the date each notice was sent to the owner and how it was sent

Filing is not the last step. No later than the fifth day after you file, send a copy to the owner, and if you are not the original contractor, to the original contractor too (§ 53.055). A missed copy is one of the listed grounds for a summary motion to remove the lien (§ 53.160(b)(3)).

The mechanics lien form builder lays out those eight items so nothing is left blank; check the result against the county clerk's own recording requirements before you file. Texas does not require a notice of intent before the affidavit, because the notice of claim already warned the owner. A short demand to the general a few weeks before your filing date still settles plenty of claims, and the notice of intent to lien generator drafts one. For the steps that are the same in every state, see how to file a mechanics lien.

Retainage and the owner's 10% reserve

Texas makes the owner hold money back whether the contract says so or not. During the work and for 30 days after completion, the owner must reserve 10 percent of the contract price, or 10 percent of the value of the work done (§ 53.101). That reserve is the pot a derivative claimant reaches with a timely affidavit, and an owner who skips it leaves its property open to a lien at least for the amount it should have kept (§ 53.105).

  • Retainage notice. If your contract provides for retainage and your monthly notices did not already claim it, send the statutory notice of claim for unpaid retainage by the earlier of the 30th day after your own contract is completed, terminated or abandoned, or the 30th day after the original contract is terminated or abandoned (§ 53.057).
  • Retainage affidavit. File by the 15th day of the third month after the month the original contract was completed, terminated or abandoned (§ 53.052(d)). The lien is good only for the amount your contract says is retained (§ 53.025).
  • The reserve. To share in the owner's 10 percent, send your notices and file an affidavit no later than the 30th day after the work is completed, the original contract terminated, or performance abandoned (§ 53.103). A claimant who gave the retainage notice can instead rely on its § 53.052 filing date (§ 53.057(f)), but the 30-day date is the safe one.

Watch the county records for an owner's affidavit of completion. It is prima facie evidence of the completion date, it must be sent to every claimant who gave a notice, and if it is filed more than 10 days after completion the filing date becomes the completion date (§ 53.106). Our retainage laws by state guide puts the Texas reserve next to other states' release rules.

Residential jobs and homesteads

A residential construction project is work on a residence: a single-family house, duplex, triplex or quadruplex, or a condo or co-op unit, owned by an adult and lived in (or meant to be) by one of the owners (§ 53.001(8)-(10)). Every derivative clock runs a month shorter there. If the house is also the owner's homestead, four more conditions sit on top (§ 53.254):

  1. 01A written contract between the owner and the person furnishing labor or material, signed before any work starts. If the owner is married, both spouses sign.
  2. 02That contract filed with the county clerk where the homestead sits. An original contractor's contract covers everyone who works under it.
  3. 03The lien affidavit topped, in at least 10-point bold, with: NOTICE: THIS IS NOT A LIEN. THIS IS ONLY AN AFFIDAVIT CLAIMING A LIEN.
  4. 04The statutory owner statement (the two-paragraph warning set out in § 53.254(g)) included in, or attached to, your notice of claim.

Lien deadline

No signed and recorded homestead contract means no lien on that house, and the owner can move to strip yours on exactly that ground (§ 53.160(b)(6)). On a remodel, ask the general for the recorded contract before you order material, not after the check bounces.

The suit deadline

A filed affidavit is security, not payment. To turn it into money you sue to foreclose, and that suit must be on file no later than the first anniversary of the last day you could have filed the affidavit (§ 53.158(a)). The year runs from your deadline, not from the day you actually filed, so filing early buys no extra time. Before the year runs out you and the record owner can sign a written extension, recorded in the same county, that pushes it to no later than the second anniversary of your filing date (§ 53.158(a-2)).

Expect paper to be attacked first. In any suit over the lien, the owner or the general can file a verified summary motion to remove it on a short list of grounds: late notice, an affidavit that misses § 53.054 or § 53.052, a missing copy under § 53.055, or a homestead defect (§ 53.160). Each is a paperwork failure, which is why the mail receipts matter as much as the invoice. Fees are awarded as equitable and just in either direction (§ 53.156).

The mechanics lien deadline calculator counts the Texas windows the same way, to the 15th of the month, from your last month of work. It shows the raw date, so move a weekend deadline to the next business day yourself, and remember that every earlier unpaid month has its own notice date. The deadlines by state table puts Texas next to California, Florida and federal jobs.

What changed in 2022

House Bill 2237 rewrote chapter 53 effective January 1, 2022. It applies only to an original contract entered into on or after that date; a job whose prime contract was signed earlier still runs on the old rules (H.B. 2237 §§ 37-38). A lot of Texas lien advice online was written for the old system. If a guide predates 2022, or does not quote the statutory notice form, treat its deadlines as suspect and check them against the current chapter.

Texas lien law before and after H.B. 2237
RuleBefore 2022Contracts from Jan 1, 2022Cite
Who gets the noticeSection headed notice to owner or original contractor; no statutory notice formOne notice of claim to the owner and the original contractor, in statutory form§ 53.056
Retainage noticeNotice of a contractual retainage claimStatutory notice of claim for unpaid retainage, 30-day deadline§ 53.057
Affidavit clock15th day of the 4th month after the day the debt accruedCounted from the month you last worked; the original contractor from the month its work ended§ 53.052
Retainage affidavitNot set in § 53.05215th day of the 3rd month after the original contract ends§ 53.052(d)
Suit to foreclose2 years after the last filing day, or 1 year after completion, whichever was later1 year after the last filing day; up to 2 years from filing by recorded agreement§ 53.158

Texas statutory lien waivers

Texas prints its lien waivers in the statute. A waiver and release is unenforceable unless it substantially complies with one of four forms, is signed by you or your agent, and, for a conditional release, there is evidence you were paid (§§ 53.281, 53.284). Nobody may make you sign an unconditional waiver for money you have not received (§ 53.283), and the two unconditional forms carry a bold warning at the top, no smaller than 10-point.

The four Texas statutory waiver and release forms
FormWhen you sign itCite
Conditional waiver and release on progress paymentSigned to get a progress check; effective once the check clears§ 53.284(b)
Unconditional waiver and release on progress paymentOnly after the progress payment is in your account§ 53.284(c)
Conditional waiver and release on final paymentSigned to get the final check; effective once it clears§ 53.284(d)
Unconditional waiver and release on final paymentOnly after final payment is received in good funds§ 53.284(e)

Two things to check before you sign. The progress forms carve out “unpaid retention, pending modifications and changes, or other items furnished”, so do not let anyone strike that line. And on a single-family house, townhouse or duplex, a waiver written into the contract before work starts can bind a sub that supplies labor, though not one that only supplies material (§ 53.282). Read the subcontract, not just the waiver.

The Texas lien waiver generator fills in the statutory text for all four forms. If you are deciding which one to hand over, the conditional vs unconditional comparison covers the trade-off.

Sources

  • Tex. Prop. Code § 53.052

    A Texas original contractor files its lien affidavit by the 15th day of the fourth month after the month work was completed, terminated or abandoned — the 15th day of the third month on residential projects. A subcontractor or supplier files by the 15th day of the fourth month after the last month it furnished work (third month on residential projects).

    Read 2026-10-18

  • Tex. Prop. Code § 53.056

    A Texas claimant who is not the original contractor must send a notice of claim for unpaid labor or materials to the owner and the original contractor for the lien to be valid, by the 15th day of the third month after the month the labor or materials were provided (the second month on residential projects).

    Read 2026-10-18

  • Tex. Prop. Code § 53.101

    Texas requires the owner to reserve 10 percent of the contract price (or 10 percent of the value of the work) during the job and for 30 days after completion — statutory retainage.

    Read 2026-10-18

  • Tex. Prop. Code § 53.103

    A Texas claimant reaches the reserved funds by sending the required notices and filing a lien affidavit no later than the 30th day after the earliest of the date the work is completed, the original contract is terminated, or the original contractor abandons performance.

    Read 2026-10-18

  • Tex. Prop. Code § 53.001(7), (13)

    An original contractor contracts with the owner directly or through the owner's agent; a subcontractor furnishes labor or materials to fulfil an obligation to an original contractor or to a subcontractor of any tier.

    Read 2026-10-18

  • Tex. Prop. Code § 53.003(b), (c), (e)

    Notices go in person, by certified mail, or by a traceable private service that confirms receipt; certified mail is complete on deposit. A deadline that falls on a Saturday, Sunday or legal holiday moves to the next day that is not one.

    Read 2026-10-18

  • Tex. Prop. Code §§ 53.021, 53.024, 53.026

    Labor, material, undelivered specially fabricated material, licensed design work, landscaping and demolition carry lien rights; a subcontractor's lien is capped at the earned share of its subcontract less payments received; a claimant hired by a sham original contractor is treated as an original contractor.

    Read 2026-10-18

  • Tex. Prop. Code §§ 53.081, 53.084

    An owner who receives a notice of claim may withhold the claimed amount from the original contractor; money it pays the original contractor after it was authorized to withhold can be recovered from it and its property once the lien is secured and the claim reduced to final judgment.

    Read 2026-10-18

  • Tex. Prop. Code § 53.106

    An owner may file an affidavit of completion; it is prima facie evidence of the completion date, and if filed more than 10 days after completion the filing date becomes the completion date.

    Read 2026-10-18

  • Tex. Prop. Code §§ 53.156, 53.160

    In a suit over a lien a party may file a verified summary motion to remove it on listed grounds, including an untimely notice, a defective or late affidavit, a missing copy of the affidavit, and homestead defects. Costs and reasonable attorney's fees are awarded as equitable and just.

    Read 2026-10-18

  • Tex. Prop. Code § 53.054

    The lien affidavit is sworn and must substantially state the amount, owner, work and (for a derivative claimant) each month worked, the hiring party, the original contractor, a legal description, the claimant's address, and the date and method of each notice sent.

    Read 2026-10-18

  • Tex. Prop. Code § 53.055

    A copy of the filed affidavit goes to the owner, and from a derivative claimant also to the original contractor, no later than the fifth day after filing.

    Read 2026-10-18

  • Tex. Prop. Code § 53.057

    A derivative claimant whose contract provides for retainage sends a notice of claim for unpaid retainage by the earlier of the 30th day after its own contract is completed, terminated or abandoned, or the 30th day after the original contract is terminated or abandoned.

    Read 2026-10-18

  • Tex. Prop. Code § 53.158

    Suit to foreclose must be brought by the first anniversary of the last day the claimant could file the affidavit, extendable to the second anniversary of filing by a recorded written agreement with the record owner.

    Read 2026-10-18

  • Tex. Prop. Code § 53.254

    A lien on a homestead needs a written contract signed before work starts (by both spouses if married) and filed with the county clerk, a 'THIS IS NOT A LIEN' header on the affidavit, and a statutory owner statement in the notice.

    Read 2026-10-18

  • Tex. Prop. Code §§ 53.281, 53.283, 53.284

    A waiver and release is unenforceable unless it substantially complies with one of four statutory forms: conditional or unconditional, on progress or final payment. An unconditional waiver may not be required before payment is received.

    Read 2026-10-18

  • Tex. H.B. 2237, 87th Leg., R.S. (2021), §§ 37-38

    H.B. 2237 (87th Leg.) rewrote the notice, affidavit and suit rules effective January 1, 2022, and applies only to original contracts entered into on or after that date; earlier contracts stay under the prior law.

    Read 2026-10-18