Skip to content

Pay-when-paid vs pay-if-paid

2026-09-045 min read

Two identical card blocks, one on a green band and one on a red band
Same shape, opposite consequence.

Both clauses tie your payment to the owner's. Only one of them can leave you unpaid forever. Here is how to tell which you signed, and what to do about it either way.

One delays, one can extinguish

A pay-when-paid clause is about timing. It says the general will pay you when the owner pays it, and courts generally read it as allowing a reasonable delay rather than removing the obligation. Eventually the general has to pay you whatever the owner does.

A pay-if-paid clause is about risk. It makes the owner's payment a condition precedent to the general's obligation. If the owner never pays, the general may never owe you — you have taken the owner's credit risk on a job whose owner you never met.

Two identical card blocks, one on green and one on red
Two identical blocks, one green-edged and one red.

How to spot which one you signed

Wording that signals each clause
SignalReads likeType
Timing words“within 10 days of receipt of payment from Owner”Pay-when-paid
Condition words“condition precedent”Pay-if-paid
Risk words“Subcontractor assumes the risk of Owner's non-payment”Pay-if-paid
Express words“express condition”, “shall not be obligated unless”Pay-if-paid

The distinction is a matter of state law as much as of wording. Some states limit or refuse to enforce pay-if-paid clauses by statute, and courts elsewhere tend to read an ambiguous clause as pay-when-paid; only clear, unmistakable language is likely to be enforced as written. Which state your job is in decides how hard you should push at award.

What to ask for at award

  1. Strike “condition precedent” and “assumes the risk” outright.
  2. Add an outside date: paid within N days of your certified application regardless of the owner.
  3. Carve out non-payment caused by the general's own default or backcharges.
  4. Preserve lien and bond rights expressly, whatever the payment clause says.
  5. Ask for the owner's funding evidence on large jobs — a normal request, often granted.

Lien rights survive separately

A payment clause governs the contract. It does not automatically waive a statutory lien or bond right, and a clause that tries to should be read carefully and struck where the state allows.

Living with one you already signed

If you are already on the job under a pay-if-paid clause, your lien and bond rights matter more than usual, because the contract claim may be conditional and the statutory claim is not. Serve the preliminary notice, track the recording deadline, and do not let a “we have not been paid either” conversation run past it.

Ask, in writing, whether the owner has paid the general for your work. The answer is discoverable eventually and asking early sometimes produces the cheque without anyone deciding whether the clause is enforceable.

A blank contract crossed by red string beside an untouched green cube
The statutory claim is the one the clause cannot condition.

Sources

  • Cal. Civ. Code § 8200

    Before recording a lien, giving a stop payment notice or claiming against a payment bond, a California claimant must give preliminary notice to the owner, the direct contractor and the construction lender. A laborer is exempt.

    Read 2026-10-18

  • 40 U.S.C. § 3133(b)(2)

    A claimant with a contract with a subcontractor but none with the prime must give the prime written notice within 90 days of its last labor or material, stating the amount claimed and who it was furnished to.

    Read 2026-10-18

  • FAR 52.232-27(a)

    On a federal construction contract, a progress payment is due 14 days after the designated billing office receives a proper payment request; an improper invoice must be returned within 7 days with reasons.

    Read 2026-10-18