Change order
CO-003 · 2026-10-18ProjectKestrel Avenue mixed-use, 1400 Kestrel Avenue
ContractSubcontract 2026-118, mechanical package
SubcontractorIronline Mechanical LLC, 220 Foundry Row, Suite 4
ContractorVantage Construction Group
ReasonOwner request
Description of change
Furnish and install two inline exhaust fans with ductwork to the roof for the tenant kitchen in Unit A-3, per the owner's request and sketch SK-M-14 dated 2026-10-12. Includes power to both fans by the electrical subcontractor. Excludes roof patching and fire-rated wrap.
| Labour | Sheet metal and fitter labour, 40 hrs | 2,900.00 |
| Material | Two inline fans, duct, hangers, roof curb | 1,500.00 |
| Equipment | Scissor lift, one week | 400.00 |
| Subcontract | Electrical: power to fans | 1,600.00 |
| Overhead and profit, own work, 15% | 720.00 | |
| Markup, subcontract work, 5% | 80.00 | |
| Total this change order | +7,200.00 | |
| Original subcontract sum | 136,000.00 |
| Net change by previously approved change orders | 4,800.00 |
| Subcontract sum before this change order | 140,800.00 |
| This change order | 7,200.00 |
| New subcontract sum | 148,000.00 |
| Contract time | +3 calendar days |
| Completion date, before / after | 2026-12-18 / 2026-12-21 |
The parties agree to the change described above. The subcontract sum is increased by $7,200.00 to $148,000.00, with +3 calendar days, moving completion to 2026-12-21. All other terms of the contract remain in force.
Subcontractor
Ironline Mechanical LLC
By (signature)
Name and title ____________________
Date ____________
Contractor
Vantage Construction Group
By (signature)
Name and title ____________________
Date ____________