Notice of delay
NOD · 2026-10-09DateOctober 9, 2026
Sent byEmail and certified mail, return receipt requested
ToVantage Construction Group, Attn: Project Manager, 18 Mercer Street
FromIronline Mechanical LLC, 220 Foundry Row, Suite 4
ProjectKestrel Avenue mixed-use — mechanical package
ContractSubcontract No. VCG-2611 dated March 2, 2026
ReNotice of delay under Article 8.3 (Delays and Extensions of Time)
This letter is written notice under Article 8.3 (Delays and Extensions of Time) of Subcontract No. VCG-2611 dated March 2, 2026 that our work on Kestrel Avenue mixed-use — mechanical package has been delayed. The delay began on October 6, 2026 and is continuing as of the date of this letter.
The delay is caused by information we needed to proceed and did not receive in time: an unanswered request for information, or design information that arrived late or incomplete. Specifically: RFI No. 031 (level 2 duct main conflicts with the beam at grid C/4) was submitted on October 6, 2026 and has not been answered. Duct mains on level 2 cannot be hung until the routing is resolved.
Based on what we know today, we estimate the delay to our work at 10 calendar days. Because the cause has not ended, this estimate will change, and we will confirm the final figure in writing when it does.
We request an extension of the contract time equal to the delay, and an adjustment of the schedule to match.
This delay is increasing our cost of performance, including extended field supervision and general conditions, equipment standby, and remobilization. We reserve our right to recover these costs and will submit a priced request once the full effect of the delay is known. Nothing in this letter waives any right we have under the contract or at law.
To limit the delay, we are taking the following steps: We have moved the level 2 crew to level 3 branch ductwork and are holding fabrication of the affected fittings so no material is built to the wrong routing.
Please confirm receipt of this notice and give us the direction or information needed to resume full production. We are available to meet at your convenience.
Sincerely,
Signature ____________________
Dana Okafor, Project Manager
Ironline Mechanical LLC